Engineered Stone Flooring Installation Guide
I. General Requirements
1. Install engineered stone tiles from the inside out, starting from the wall farthest from the door and working back toward the door.
2. Border tiles and baseboards should align with the joints of the floor tiles.
3. Provide rain shields near doors and windows to prevent water accumulation. Ensure water supply, electricity, tools and safety measures are all in place.
II. Thin-Bed Method on Rigid Substrate
1. Install only on a fully cured rigid substrate. Concrete subfloors must cure for at least 28 days; cement mortar screeds for at least 14 days.
2. Use a two-component cementitious adhesive as the bonding material.
3. The rigid substrate must meet the following requirements:
1) Surface flatness deviation shall not exceed 3 mm over a 2 m straightedge. If this is not met, level with a polymer-modified cement mortar.
2) No standing water; substrate moisture content shall not exceed 8%.
3) The surface must be sound, clean and free of oil, paint, dust or other bond-breaking contaminants.
4) Substrate strength:
① Concrete subfloor grade ≥ C20.
② Screed mortar grade ≥ M15; thickness ≥ 20 mm; cement-to-sand ratio approximately 1:2.
4. Follow the installation process flow shown below:

5. Key installation steps:
1) Mechanically roughen (scabble) the substrate surface.
2) Snap cross control lines on the substrate according to the layout drawing, and extend the lines up the base of the walls.
3) Mix the adhesive according to the manufacturer's instructions. Mix only the amount that can be used within the product's pot life.
4) On the substrate, use the straight edge of a 10 mm × 10 mm notched trowel to spread a flat layer of adhesive. Then, holding the trowel at a 45° angle, comb with the notched edge to create full, uninterrupted ridges. The total adhesive thickness should be 3–4 mm.
5) Clean the back of each stone panel with a dry cloth or brush to remove dust, oil, rust and other contaminants. Using the straight edge of a 12 mm × 12 mm notched trowel, spread a flat layer of adhesive on the back. Then, at a 45° angle, comb ridges with the notched edge, achieving a thickness of 3–4 mm. Ensure the edges and corners are fully coated and slightly beveled.
6) Lower the tile into place so that the direction of the ridges on the tile back is parallel to the ridges on the substrate, fitting the ridges into the grooves. Press firmly and manipulate the tile to achieve the required flatness and level.
7) Maintain the joint width specified in the design between tiles, using joint spacers to hold them in place. Install movement joints as shown on the drawings; these joints must extend down to the substrate.
8) After every 30 m² of installation, gently tap each tile to check for hollow sounds. If any hollow areas are found, remove and relay the tile immediately.
9) Grouting should be carried out no sooner than 28 days after installation, or when the adhesive has completely cured. Grouting requirements:
① Clean the joints, then pack them uniformly with a reactive resin grout that matches the stone color. The joint must be fully filled and strongly bonded.
② Clean out movement joints down to the substrate. Before floor finishing, fill them with a neutral-cure, weather-resistant silicone sealant. After finishing, install a U-channel or similar buffer profile.
III. Soft-Bed Method
1. After the on-site mortar screed has been laid, use a one-component, moisture-curing polyurethane adhesive and follow the process flow below:

2. Key installation steps:
1) Clean the concrete subfloor, removing laitance, mortar droppings, oil, paint, sealers and any other bond-inhibiting materials. Chip away any high spots.
2) Using the reference level lines on the wall, snap the finished floor level lines. Except for wet areas, the entire floor on one level should have a uniform elevation.
3) Screed layer:
① Brush a neat cement slurry (water/cement ratio 0.4–0.5) onto the concrete subfloor. Do not spread a larger area than can be covered with mortar before the slurry dries.
② Place the screed mortar. The uncompacted thickness should be such that when a tile is placed on it the tile surface is 3–4 mm above the finished floor line. Use ordinary Portland cement of grade 32.5 or higher; the sand should be medium to coarse, with a silt content below 3% and no organic matter. Mix cement and sand at a ratio of about 1:2 with water until the mixture holds its shape when squeezed in the hand but crumbles easily when poked. Level with a straightedge and tamp firm.
4) Snap cross control lines. Dry-lay the stone panels on the mortar bed, pressing and vibrating them to check color, size and edge alignment. Exchange tiles if necessary.
5) Apply adhesive:
① Prepare the one-component, moisture-curing polyurethane adhesive following the instructions.
② Lift the dry-laid panel. Apply small dabs of adhesive to the mortar bed at the four corners where the tile will sit. Clean the back of the stone panel. Using a 6 mm × 6 mm notched trowel, spread adhesive on the back to a thickness of 2–3 mm. Fill and bevel the edges.
6) Place the panel onto the screed, press it firmly and tap it to level. Avoid harsh or heavy hammering.
7) Maintain design joint widths with spacers, and install movement joints extending to the substrate as specified.
8) Check for hollow sounds every 30 m²; relay any tile that sounds hollow.
9) Grout after 28 days or after full adhesive cure, following the same grouting specifications as the thin-bed method.
IV. Post-Installation Protection
Immediately after installation, cover the entire floor with a continuous, breathable protective layer such as gypsum board, fiberboard, hardboard or composite wood panels. This prevents scratches, stains and vibration from subsequent work. Do not walk on the floor for 3 days. For 7 days, avoid moving materials, placing ladders, or bringing heavy equipment onto the floor.